Projects

Civil engineering Project Portfolio

back to Projects TOP

Current search settings
Tottori Dam construction three-surface channel construction (743)
Tottori Dam construction three-surface channel construction (743)
  • [Products & Services]
    "TACOM"-Fabric formwork-
  • [Purpose / Application]
  • [completion of construction]
    September 2011
  • [Location]
    Tottori
Tottori Reclamation Project Piping Slope Protection (742)
Tottori Reclamation Project Piping Slope Protection (742)
  • [Products & Services]
    "TACOM"-Fabric formwork-
  • [Purpose / Application]
    Slope protection
  • [completion of construction]
    March 2010
  • [Location]
    Tottori
Tottori Dam construction river slope protection work (741)
Tottori Dam construction river slope protection work (741)
  • [Products & Services]
    "TACOM"-Fabric formwork-
  • [Purpose / Application]
    Slope protection
  • [completion of construction]
    June 2007
  • [Location]
    Tottori
Erosion control weir river channel switching work (1110)
Erosion control weir river channel switching work (1110)
  • [Products & Services]
    "Max Wall"-Continuous box-type steel frame-
  • [Purpose / Application]
    Temporary construction / Rockfall protection / Earth retaining
  • [completion of construction]
    June 2020
  • [Location]
    Tottori
Tottori Repair work outside revetment(969)
Tottori Repair work outside revetment(969)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    January 2014
  • [Location]
    Tottori
Tottori Port Quay Construction (965)
Tottori Port Quay Construction (965)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    January 2018
  • [Location]
    Tottori
Tottori Scenic Road Widening 1 (881)
Tottori Scenic Road Widening 1 (881)
  • [Products & Services]
    "EDO-EPS Method"-Lightweight embankment method-
  • [Purpose / Application]
    Lightweight embankment / Reinforced soil
  • [completion of construction]
    June 2005
  • [Location]
    Tottori
Tottori Scenic Road Widening 2 (882)
Tottori Scenic Road Widening 2 (882)
  • [Products & Services]
    "EDO-EPS Method"-Lightweight embankment method-
  • [Purpose / Application]
    Lightweight embankment / Reinforced soil
  • [completion of construction]
    August 2005
  • [Location]
    Tottori
Tottori Temporary road earthwork (830)
Tottori Temporary road earthwork (830)
  • [Products & Services]
    "Max Wall"-Continuous box-type steel frame-
  • [Purpose / Application]
    Temporary construction / Rockfall protection / Earth retaining
  • [completion of construction]
    July 2016
  • [Location]
    Tottori
Nakami-Shimada Seawall Outer Repair Work (Yonago Port)
Nakami-Shimada Seawall Outer Repair Work (Yonago Port)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    January 2014
  • [Location]
    Tottori
Sakaiminato Outer Port Takeuchi South Area Quay (-10m) Construction (Part 2)
Sakaiminato Outer Port Takeuchi South Area Quay (-10m) Construction (Part 2)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    January 2018
  • [Location]
    Tottori