Projects

Civil engineering Project Portfolio

back to Projects TOP

Current search settings
Mie Pref. Regulating reservoir revetment slope construction (595)
Mie Pref. Regulating reservoir revetment slope construction (595)
  • [Products & Services]
    "TACOM"-Fabric formwork-
  • [Purpose / Application]
    Slope protection
  • [completion of construction]
    September 2016
  • [Location]
    Mie
Mie Prefecture River improvement slope protection work 2(594)
Mie Prefecture River improvement slope protection work 2(594)
  • [Products & Services]
    "TACOM"-Fabric formwork-
  • [Purpose / Application]
    Slope protection
  • [completion of construction]
    February 2013
  • [Location]
    Mie
Mie Prefecture River improvement slope protection1(593)
Mie Prefecture River improvement slope protection1(593)
  • [Products & Services]
    "TACOM"-Fabric formwork-
  • [Purpose / Application]
    Slope protection
  • [completion of construction]
    October 2013
  • [Location]
    Mie
Mie Pref. Removal of obstruction to regulating reservoir (592)
Mie Pref. Removal of obstruction to regulating reservoir (592)
  • [Products & Services]
    "TACOM"-Fabric formwork-
  • [Purpose / Application]
    Rivers / Reservoirs / Regulating reservoirs
  • [completion of construction]
    January 2015
  • [Location]
    Mie
Mie Prefecture Regulating reservoir slope protection work (591)
Mie Prefecture Regulating reservoir slope protection work (591)
  • [Products & Services]
    "TACOM"-Fabric formwork-
  • [Purpose / Application]
    Slope protection
  • [completion of construction]
    March 2009
  • [Location]
    Mie
Mie Prefecture, river revetment slope protection work (1100)
Mie Prefecture, river revetment slope protection work (1100)
  • [Products & Services]
    Honeycomb Frame Spike
  • [Purpose / Application]
    Slope protection
  • [completion of construction]
    November 1998
  • [Location]
    Mie
Mie National Highway Public Works Facility Protection (1044)
Mie National Highway Public Works Facility Protection (1044)
  • [Products & Services]
    "SAM Method"-Rockfall buffer method-
  • [Purpose / Application]
    Temporary construction / Rockfall protection / Earth retaining
  • [completion of construction]
    January 2009
  • [Location]
    Mie
Mie Prefecture Road bridge construction (959)
Mie Prefecture Road bridge construction (959)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    October 2012
  • [Location]
    Mie
Mie Prefecture Hutou Bridge Lower Structure Construction(958)
Mie Prefecture Hutou Bridge Lower Structure Construction(958)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    April 2013
  • [Location]
    Mie
Mie Prefecture Levee maintenance work (957)
Mie Prefecture Levee maintenance work (957)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    June 2015
  • [Location]
    Mie
Mie Prefecture Bridge substructure construction1(954)
Mie Prefecture Bridge substructure construction1(954)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    May 2016
  • [Location]
    Mie
Mie Prefecture Bridge substructure construction3(956)
Mie Prefecture Bridge substructure construction3(956)
  • [Products & Services]
    "Silt Protector"-Pollution control membrane-
  • [Purpose / Application]
    Pollution preventing measures
  • [completion of construction]
    May 2017
  • [Location]
    Mie